So Ken,

What you are saying is that basically we have all thwe hashfast customers?!?!?!

Almost certainly not, VMC will be splitting the HashLast customers with PepperMining which have a similar product but better reputation.

Peppermining has more than a better reputation, they actually provide support and working contact information to their customers.

I'd recommend taking a look at the VMC Sales thread in the harware section to get an idea of what people are up against.  
hero member
Activity: 487
Merit: 500
Are You Shpongled?
WOW. 2 months since the farm deployment began and the AC is still an issue. How could Ken lack the foresight to fix the AC when it has been a recurring problem and it would cost significantly less to replace the whole system than the lost revenue as an opportunity cost.

Also the website is still not fixed. Fucking unbelievable. No financials is disappointing but I would be lying if I said I was surprised.
member
Activity: 106
Merit: 10
Still no proper financials?

There is a reason why publicly traded companies are required to release such information...
full member
Activity: 142
Merit: 100
Weekly Update: 5/29/2014

Sorry for the late update.  I have been busy working in our DC and taking care of our relationship with hashfast in light of their bankruptcy.

Datacenter:

We are having some problems keeping our AC running, this is why we have not increased the hashrate.  The project manager has now got the AC people working to correct the problem.

AMC:

I will finish the shares transfers as soon as I can.  I expect this to be in the next few days.

VMC:

We are working to build and sell boards to hashfast customers.



Thanks for the update.

Can we please get some back of the envelope numbers for assets and liabilities?

What was the net effect to date of:

eASIC relationship
People's ASIC acquisition
Ken+family salary
DC
Prospector boards
Gold rush boards

What does inventory look like?

Visibility to / confidence of distributing preferential dividend before any additional plow-back?

An effective manager should have all of this information at his fingertips.
member
Activity: 98
Merit: 10
So Ken,

What you are saying is that basically we have all thwe hashfast customers?!?!?!

Almost certainly not, VMC will be splitting the HashLast customers with PepperMining which have a similar product but better reputation.
sr. member
Activity: 517
Merit: 250
So Ken,

What you are saying is that basically we have all thwe hashfast customers?!?!?!
hero member
Activity: 532
Merit: 500
https://karatcoin.co
Weekly Update: 5/29/2014

Sorry for the late update.  I have been busy working in our DC and taking care of our relationship with hashfast in light of their bankruptcy.

Datacenter:

We are having some problems keeping our AC running, this is why we have not increased the hashrate.  The project manager has now got the AC people working to correct the problem.

AMC:

I will finish the shares transfers as soon as I can.  I expect this to be in the next few days.

VMC:

We are working to build and sell boards to hashfast customers.




Follow up questions:

Datacenter:
How much more hashrate will be be able to fit into this DC once the AC is working properly?

VMC:
What kind of volume are we talking with the board sales? Is a contract involved?

member
Activity: 98
Merit: 10
Will dividends be disbursed following this final transfer?
sr. member
Activity: 476
Merit: 250
Weekly Update: 5/29/2014

Sorry for the late update.  I have been busy working in our DC and taking care of our relationship with hashfast in light of their bankruptcy.

Datacenter:

We are having some problems keeping our AC running, this is why we have not increased the hashrate.  The project manager has now got the AC people working to correct the problem.

AMC:

I will finish the shares transfers as soon as I can.  I expect this to be in the next few days.

VMC:

We are working to build and sell boards to hashfast customers.

member
Activity: 98
Merit: 10
The lack of updates is certainly disconcerting, but I'm hoping to hear something from Ken about those 1000 chips that Hashfast allegedly mailed out yesterday (the assumption, which is obviously an assumption but I suppose in the current environment it behooves me to explicitly state so, is that VMC, ActM, or whichever affiliated entity has purchased some or all of those chips).

Also, If Bargraphics's offer still stands, I don't see why we shouldn't throw the nearly 1 PH/s of hardware that ActM has into action.
hero member
Activity: 658
Merit: 500
decentralize EVERYTHING...
Another missed deadline?

Looks like the heist has officially begun.
member
Activity: 70
Merit: 10
oh its been deleted, i enjoyed that bit chat.



As always, quoting known and listed trolls will get your comments deleted.

Thanks!
sr. member
Activity: 242
Merit: 250
oh its been deleted, i enjoyed that bit chat.

hero member
Activity: 532
Merit: 500
https://karatcoin.co
all i can say is my god.

with todays technology , you can log into bitcointalk while on bed before going sleep, and formulate the words to post, whether an update on data center or other little thing.

ken used to be active and reply here immediately, during last year. now it seems opposite.

Well, let's not get ahead of ourselves. He did post five days ago informing us why he missed last Wednesday's update.

I agree with your general sentiment.
sr. member
Activity: 242
Merit: 250
all i can say is my god.

with todays technology , you can log into bitcointalk while on bed before going sleep, and formulate the words to post, whether an update on data center or other little thing.

ken used to be active and reply here immediately, during last year. now it seems opposite.
hero member
Activity: 532
Merit: 500
https://karatcoin.co
Another missed deadline?

What's worse to me is that there isn't even an attempt at communicating that we shouldn't expect a Wednesday update.

I can't believe Ken is too busy to reply to us and post.


I'm sure he's working on the hashrate, but it takes 30 seconds to pop in and let us know he doesn't have time for a full update and to reschedule. I'm annoyed.   Wink
newbie
Activity: 17
Merit: 0
Where's the refund ?
Where's the Wednesday update?

 Huh Huh Huh Huh
legendary
Activity: 1176
Merit: 1015
Another missed deadline?

What's worse to me is that there isn't even an attempt at communicating that we shouldn't expect a Wednesday update.

I can't believe Ken is too busy to reply to us and post.
hero member
Activity: 532
Merit: 500
https://karatcoin.co
Another missed deadline?

What's worse to me is that there isn't even an attempt at communicating that we shouldn't expect a Wednesday update.
member
Activity: 106
Merit: 10
Another missed deadline?