Received a few minutes ago via email:
"Hello one and all.
First I want to thank everyone for the positivity we've been experiencing both via online channels as well as at the open house events! I've also received a TON of really supportive energy from the community and I can't thank you enough... it really keeps us all going when there's huge amounts of hard work to do.
Unfortunately, I have to announce a delay in construction which will block us from issuing Batch 3 tokens on time. We've been working tirelessly to bring pods out of the ground, but several conditions related to the construction and planning process have introduced additional delays that are now clearly keeping us from turning up as many pods as planned for Sept and October. The process of building the pods and deploying equipment is going as expected. The real time-impact has to do with permitting, planning and inspections. Our GigaPods were virtually the first purpose-built blockchain processing facilities these people had ever seen, and it has caused small delays at every turn.
The good news is that we are through most of that. We have educated the stakeholders in two counties about our GigaPod construction processes and how the finished product looks and works. I expect these types of delays to become less and less now that it has become familiar to them.
Our construction crews and electricians are getting pod construction down to a science. We will continue to run day and night crews to bring up as much power capacity as possible, as soon as possible.
On the topic of hardware arriving in September: there's significantly less equipment arriving in September than the amount of power we are building, so it becomes a little easier to see through to getting it all running. I expect to have much of the September hardware running soon after it comes in. Because the construction process is not a perfect science, its hard to know exactly when backed up gear will be put into service. To mitigate the situation, GW is seeking any and all alternative solutions to get gear running as soon as possible so that it won't just sit on the warehouse shelves. As a miner myself, I know just how important that is to our customers.
I'm sure that questions and concerns will still linger, so I am planning to make myself personally available on chat channels in order to answer questions whether to the group or to me personally. I do appreciate your continued patience and support. I want you to know that the whole GW team is directly focused on getting tokens issued and miners running as fast as humanly possible.
It’s always hard to maintain communications and transparency during the chaotic startup phase, but we are committed to improving on this front. We are improving our support to clients slower than we and everyone wanted but are progressing on that. Within the next 3 to 4 business days I will begin releasing weekly updates to help everyone track progress along the new timelines. I aim to improve confidence in Giga Watt and significantly reduce concerns you may have going forward.
Best Regards
Dave Carlson, CEO
Giga Watt, Inc."
Tnx for the info but do you mean this with an official statement? This is a message from Mr Carlson to someone with very little info in it, firstly I believe a serious company should inform (all) their custumors directly i.e. email, statement on the official website etc.
Secondly everyone is just happy with some deficient "timeline" which is not even been updated regularly. According to the Giga-Watt strategy there should be 10+ Pods right now, but they are keeping us satisfied with some updates on 4 Pods...
WtF???
don´t wanna FUD but with every day I am getting more and more suspecious of this company. I guess this is maybe a worthless ICO after all