Via Jody's blog, we can conclude the minirig line made ZERO progress from roughly August 15th until today. It seems ONE 500 GH/s unit has been completed since then (as seen on Jody's Update yesterday). If only one 500 GH/s unit has been completed since the 15th, which is 8 days...How, at ONE 500 GH/s unit EVERY 8 DAYS, will BFL ever complete the backlog?
If BFL is purposely slowing the Minirig line, to force big-money investors to switch their investment to the Monarch line, this would be very troubling.
I welcome BFL to clarify why this line, which so much money has been dumped into by customers, is moving so slowly...Neglect, lack of coordination, or fraud?
Also, since I have 1.5 TH/s to my order...Can I assume, at one 500GH/s rig every 8 days, my order will take 24 DAYS to build and fulfill?
Thanks for your time
PS: I'm not an angry troll, I've invested in the Minirig line and I'm extremely concerned at the lack of progress. And seemingly no effort to correct it..
Are no other MiniRig purchasers as concerned as I am?
BFL says you guys won't ask for refunds. Maybe they don't feel like they need to bother making your stuff.
From Jody's Blog
Jalapenos: January 21, 2013
Little Singles: Oct. 11, 2012 pay date
Singles: July 5, 2012 pay date
MiniRigs: MiniRigs for June 23 (2nd 500gh/s unit) and July 28 for 1st 500 gh/s
Observations:
People who ordered Jalapenos usually only ordered one.
People who ordered Singles often ordered 3, 6, 12 or more.
People who ordered in January hardly wrote us any emails.
People who order MiniRigs don't ask for refunds
----------------------
Apparently that's the excuse for the line moving at 1 500GH/s unit every 8 days? We don't ask for refunds so no incentive to go faster?If they had stated that 1.5TH Minirig orders, once they knew they had become 3 500GH units, would take 24 days to be completed...I believe people would have acted differently.