As usual, you are an idiot, greyhawk. Do you even try to make posts that fit reality or do you just post shit to see what you can get away with? Are you trying to take PuertoRetard and CreativeIdiot's place in the top dumbasses of BitcoinTalk?
Here is the current projected timeline:
Leave for the fab ~ Feb 1st or 2nd
Acquire 6 wafers earliest Feb 4th - Latest Feb 8th
Transport wafers same day to bumping facility
2 days in bumping facility
Transport to substrate and packaging
1 - 2 days for substrate and packaging
Transport to assembly house
< 24 hours at assembly house
~1 day for chip verification/testing
Transport to Kansas City
Bulk assembly / send out demo units
Ship bulk units
Our biggest hold up right now is the bumping and we have that taken care of, but we are trying to get that expedited and shave some days off (hopefully up to 7 days! Probably not that much though.). I'm waiting to hear back with regards to the expedite request and if they can speed thing up before I post the timeline, as it will affect it by up to five days depending on the outcome of that.
If you're not trying to shave off 7 days off the 2 days in bumping, maybe learn how to write better?