Except Fab 10 is 130nm and I haven't see any news about it being upgraded to 110nm or smaller.
Presently, TSMC's Fab10 mainly uses 180-nm process and turns out about 45,000 wafers per month. After the capacity expansion is completed, the foundry factory's monthly output will be expanded to over 49,000 units at the end of this year. Furthermore, the firm is also going to upgrade the factory's production process into 130-nm, which will further drive up its maximum output.
http://www.thefreelibrary.com/TSMC+ready+to+expand+output+at+Fab10+in+Shanghai.-a0235281019Thanks good call. If it's anything like last year, the chips flew into Shanghai's Export Processing Zone (EPZ) for customs processing. Not sure what happened this time, but they expected only a 2-3 day additional customs clearance delay last time:
Let's be frank. We ran into a potential delay of 4-7 days.
What does this mean?
We when taped out the chips to TSMC we had a "projected out date" of Jan 3, 2013 which is on schedule with our late dec. / early jan. demonstration dates. Now however after this week's website update our "projected out date" has changed to Jan 7th, 2013 and "committed date" has been revealed to be Jan 10th, 2013. TSMC did not give us a reason for this, but as a small customer you are really at the mercy of bigger customers running higher priority lots. e.g. "super hot lot" The "committed date" is the promised date of delivery, it is very unusual for TSMC to break their "committed date", so we expect our chips to ship on or before Jan 10th, 2013.
Another potential problem is Customs clearing, the packaging company Fujitsu is located in Shanghai's Export Processing Zone (EPZ), while the packaging itself will not see delays, it may take an additional 2-3 days to clear Customs. To make up for this, if it occurs, we will be flying down to Shanghai to the demonstration in the EPZ instead of waiting for the shipping to the factory for assembly.
With all this happening, it has burned through the 1 week additional leeway time we originally left out. I must say it will be difficulty for us to ship on Jan 14th, we however expect to ship around Jan 18 ~ 20.
https://bitcointalksearch.org/topic/announcement-avalon-asic-development-status-batch-1-120184